Sunday, 21 October 2007

Update: Wiring & Testing

The last couple of weeks have seen the tracklaying and wiring completed, with the layout being tested on both DC and DCC (Digital Command Control).

This week I plan to:
1. Carve the cork track underlay to provide clearance for the platforms to be installed.
2. Secure the formers for the retaining walls.
3. Start contruction work on the bridge formers.

The week after I hope to start installing the retaining walls and the platforms. That's about all for now. I'll let you know how I get on later this week on Friday

No comments: